| Services: |
Engineering and Construction Management |
| Challenges: |
A significant effort was required for hydraulic analysis to correct
some existing hydraulic deficiencies; to correctly incorporate the
new facilities with the existing facilities in order to prevent short circuiting
of the wastewater through the plant; and to increase the peak hydraulic capacity
of the plant to approximately 6.0 MGD. |